City of Nowthen · 2025 budget
Road Improvement Fund
$555,400 budgeted for 2025Source checked
Budget account/object: Professional services; Repair & Maintenance; Calcium Chloride; Improvements
In the adopted budget
From Road Improvement Fund — fund statement. Each line links to the PDF page it was read from.
| Professional services | 414-43414-310 | $25,000 | source p.22 | |
| Repair & Maintenance | 414-43414-405 | $100,000 | source p.22 | |
| Calcium Chloride | 414-43414-450 | $50,000 | source p.22 | |
| Improvements | 414-43414-510 | $380,400 | source p.22 |
Bills that were paid
Invoices and claims from meeting records matching this item. AI-extracted, so check the linked page before relying on a figure.
North Valley 2019 Street Improvement Project invoiceTuesday, August 13, 2019$712,134
North Valley 2019 Road Improvement Project claimTuesday, August 13, 2019$255,843
Mentioned in meetings
Other dollar figures about this item from meeting records, such as estimates, contracts, and reports. AI-extracted, so check the linked page before relying on a figure.
Estimated total overlay improvement costFY 2025Tuesday, June 17, 2025p.1$366,080
2025 Overlay total project estimate stated in minutesFY 2025Tuesday, February 11, 2025p.1$403,480
2025 Overlay feasibility report estimated project costFY 2025Tuesday, February 11, 2025p.1$366,080
2025 road construction budget allowedFY 2025Tuesday, January 14, 2025p.1$380,000
2025 Street Renewal Capital budgetFY 2025Tuesday, December 10, 2024p.34$555,400
2025 street improvements budgetFY 2025Tuesday, December 10, 2024p.21$380,400
2025 road improvement preliminary estimateFY 2025Tuesday, November 12, 2024p.147$510,000
Road improvement bond issue 2025FY 2025Monday, September 16, 2024p.27$978,040
Road improvement total expenditures 2025FY 2025Monday, September 16, 2024p.27$555,400
2025 Street Renewal Improvement Fund expendituresFY 2025Monday, July 29, 2024p.24$912,000
2025 Street Renewal infrastructureFY 2025Monday, July 29, 2024p.24$752,000
FIN-025 Road improvement issue bonds 2025FY 2025Monday, May 6, 2024p.21$1,890,970
Road Improvement Fund planned bond issueFY 2025Tuesday, August 8, 2023$1,750,000
Overlay asphalt surface technologies base plus alternate bidFY 2026Thursday, June 11, 2026p.3$470,999
Overlay north valley base plus alternate bidFY 2026Thursday, June 11, 2026p.3$459,300
Overlay knife river base plus alternate bidFY 2026Thursday, June 11, 2026p.3$438,576
Overlay asphalt surface technologies base bidFY 2026Thursday, June 11, 2026p.3$430,448
Overlay capital paving base plus alternate contractFY 2026Thursday, June 11, 2026p.3$427,589
Overlay north valley base bidFY 2026Thursday, June 11, 2026p.3$421,528
Plow truck not to exceed amountFY 2027Thursday, June 11, 2026p.31$400,000
Overlay knife river base bidFY 2026Thursday, June 11, 2026p.3$396,208
Overlay capital paving base bidFY 2026Thursday, June 11, 2026p.3$390,646
2027 road improvement bond issueFY 2027Tuesday, June 9, 2026p.49$1,140,000
2027 road improvement projectFY 2027Tuesday, June 9, 2026p.49$520,000
2026-2027 road improvements totalFY 2027Thursday, May 28, 2026p.10$1,125,000
Road improvement bond issueFY 2027Thursday, May 28, 2026p.10$1,084,000
Long-term annual road improvement targetThursday, May 28, 2026p.10$1,000,000
2028 RIP 184th and Tiger StreetFY 2028Thursday, May 28, 2026p.14$480,000
Future street improvement spending targetFY 2029Tuesday, May 19, 2026p.4$1,000,000
Road improvement project 2030FY 2030Tuesday, May 19, 2026p.22$820,000
Ask a question about this in search to read the full meeting discussions. What the labels on this page mean.