Anoka County Transportation Committee meeting, April 6, 2015
CommitteeMonday, April 6, 2015
Agenda items below come from the agenda. An agenda shows what was proposed, not what passed.
On the agenda (from the posted agenda)
1.Consider recommending approval of Resolution #2015-TR09, a resolution entering into Contract #C0004182, MnDOT Advance Construction Agreement #1000436 for Project SP 002-624-026, the reconstruction of CSAH 24 (Bridge…
2.Consider recommending award of Contract #C0004163 to Doyle Conner Co., based on their low bid of $2,972,822.87 for Anoka County Project #SAP 002-622-034, the concrete overlay of CSAH 22 (Viking Blvd) from CSAH 78…
3.Consider recommending approval to award Contract #C0004180 to the lowest responsible bidder for Anoka County Construction Project 002-683-004, the TH10 / CSAH 83 (Armstrong Blvd) Interchange project, in the City of…
4.Consider recommending approval to increase Contract #C0004130 with SRF Consulting Group, Inc., by $335,000 due to scope and required Federal design standard changes, to a total of $2,180,465.20 for Project SP…
5.Consider authorizing the County Engineer to negotiate an agreement with CenturyLink for relocation of utilities in their own easement on 002-683-004, the US 10 at Armstrong Blvd Interchange
6.Consider recommending approval of Purchase of Service Agreement #C0004183 with Erickson Engineering for the design of four bridge expansion joint repair plans, in the amount of $29,000.00, and further authorize the…
7.Consider recommending approval to enter into a License Agreement C0004169-LA with Martin T. Moritz and Caron L. Moritz in association with project SAP 002-62-028 on CSAH 22 (Viking Blvd.) from County Road 65 (Baugh…
8.Consider recommending the Management Committee approve the restructure of the Engineering section
9.Review Purchase of Service Agreement #C0004156 in the amount of $21,500, with Short Elliott Hendrickson, Inc. (S.E.H.) for Traffic Signal Design Services for Project SP 002-611- 034, the reconstruction of Foley Blvd…
10.Discuss cost and schedule issues associated with the proposed Hanson Boulevard (CSAH 78) grade separation project over the Burlington Northern Santa Fe (BNSF) Railroad in the City of Coon Rapids
11.Receive First Quarter (January, February and March) update for Commute Solutions / Anoka County Transportation Management Organization (TMO)
12.Review of Corridor Updates and Project Progress
- a)The County will let a contract and construct the Project in accordance with Agency Agreement No. 00002. Payment provisions for federally eligible costs will be as stated herein
- b)It is estimated that the total cost of the Project is $ 3,009,685.75 and that the anticipated federal funding will be capped at $ 1,478,400. The remaining share will be paid by the County
- c)The County will pay any part of the cost or expense of the Project that is not paid by federal funds
- d)Request for reimbursement of the federal aid share of the federally eligible costs can be made any time after the work is completed, however payment may not be made until after October 1, 2015. It could be earlier if…
- e)If the project is converted to federal funding before completion and final acceptance, requests for reimbursement will occur as partial estimates in accordance with Agency Agreement No. 00002
- f)Under Minnesota Statutes § 16C.05, subd. 5, the County's books, records, documents, and accounting procedures and practices relevant to this Agreement are subject to examination by the State and the State Auditor or…
13.Redesign due to 146th Cul-de-sac location moving; additional survey at new location was needed
14.Resolution of traffic volumes; which were questioned by MNDOT in pavement designs
15.Due to additional parcels affected by the revised design, additional Right of way coordination between the City of Ramsey, Anoka County, MnDOT, and local land owners was required to ensure all properties were acquired…
16.Additional concept work to understand how far we could move the NE ramp in along the railroad to avoid CIP walls
17.Developed multiple driveway concepts for Furniture Store
18.Developed multiple driveway concepts for US Bank
19.Developed 32 parcel sketches, 23 were assumed in original scope
20.Multiple iterations of sanitary sewer design to accommodate other design revisions
21.Additional assessment for McDonalds site and retaining wall & Utility easement
22.Coordination and preparation of RR Easement not included in original scope
23.Existing Watermain assessment under CIP wall/coordination with Braun
24.Redesign due to footing of Wall A being lowered near the existing watermain
25.Additional environmental borings requested by MnDOT were performed
26.Coordination/ meeting with MnDOT Construction Staff, revisions to plan per changes
27.Draft ROW PIF Letter was prepared
28.Received ADA comments from MNDOT late in the process which caused rework and changes to the plan
29.Recognizing the geometric layout was completed prior to many of the project details being fully developed, some items required design revisions and coordination with MnDOT to get plan approval. These changes were made…
30.and crosses over the Rum River. Minor repairs were performed on the bridge in 1994
Detailed briefing not yet prepared.
Sources
Documents and recordings archived for this meeting, when available.
Packet
Not in this archive
The supporting materials the board reviewed.
Minutes
Not in this archive
The official record of what happened.
The summary on this page is AI-extracted and may need correction. The PDFs and the meeting recording are the official record. What do the trust labels mean?